Probability Estimate in PERT Analysis

Filter Course


Probability Estimate in PERT Analysis

Published by: Dikshya

Published date: 25 Jul 2023

Probability Estimate in PERT Analysis

Probability Estimate in PERT Analysis

Introduction:

PERT (Program Evaluation and Review Technique) is a project management tool used to estimate the time required to complete a project. It involves analyzing and estimating three time estimates for each activity in a project: Optimistic (O), Most Likely (M), and Pessimistic (P). These estimates are then used to calculate the expected duration and variability of the project. The probability estimate is a crucial aspect of PERT analysis as it helps project managers in making informed decisions and managing project risks effectively.

Probability Estimate in PERT Analysis: In PERT analysis, the probability estimate refers to the likelihood of completing a project within a specific duration. This estimate is based on the Expected Duration (TE) and Standard Deviation (σ) calculated from the three time estimates (O, M, and P) for each activity.

1. Expected Duration (TE): The Expected Duration (TE) of an activity is calculated using the following formula: TE = (O + 4M + P) / 6

Where:

  • O: Optimistic Time Estimate
  • M: Most Likely Time Estimate
  • P: Pessimistic Time Estimate

2. Standard Deviation (σ): The Standard Deviation (σ) of an activity is calculated using the following formula: σ = (P - O) / 6

3. Probability of Completing within a Specific Duration: Once the Expected Duration and Standard Deviation are calculated for each activity, the overall Expected Duration (TED) and Variance (V) for the entire project can be determined. The probability of completing the project within a certain duration can then be estimated using the normal distribution curve.

The normal distribution curve represents the probability distribution of the project completion time. It is assumed that the completion time follows a normal or bell-shaped distribution. The area under the curve between two points represents the probability of completing the project within that time range.

4. Z-Score: To find the probability of completing the project within a specific duration, a Z-Score is calculated. The Z-Score is a measure of how many standard deviations an observed value is from the mean. It is calculated using the formula: Z = (X - TED) / σ

Where:

  • X: The specific duration for which we want to find the probability of completion.
  • TED: Total Expected Duration of the project.
  • σ: Standard Deviation of the project duration.

5. Probability Calculation: Once the Z-Score is calculated, it can be looked up in the standard normal distribution table to find the corresponding probability of completion.

  • If Z-Score is negative, the probability represents the likelihood of completing the project before the specific duration.
  • If Z-Score is positive, the probability represents the likelihood of completing the project after the specific duration.

Conclusion:

Probability estimates in PERT analysis provide valuable insights into the likelihood of completing a project within a given timeframe. By considering the probabilities, project managers can make informed decisions, set realistic expectations, and implement appropriate risk management strategies. PERT analysis, with its focus on probability estimates, helps in better planning, execution, and successful completion of complex projects.